Project Overview:This steel structure project spans from axis 1-1 to 1-20 (North to South) and axis 1-A to 1-G (West to East).
Read More
Yoshida New Materials Phase I Plant Project
Total Area: 17,000 m²
Plant 4# & 5#: 6,000 m² each
Construction Location: Nancun Town, Zezhou County, Jincheng City
Structural Form: Light Steel Structure, Portal Frame
Frame Type: Three-span, six-slope roof
Eave Height: 11.30 m
Total Length: 83.40 m
Total Width: 72.70 m
Roof Slope: 1:20
Foundation Type: Reinforced Concrete Independent Foundation
Plant 2# & 3#: 2,500 m² each
Material Specifications:
Portal Frame: C355B Grade Steel
Bracing, Purlins, Wall Girts, Channel Steel, Angle Steel, Round Steel: Q235B Grade Steel
Unspecified Steel Components: Same as Portal Frame (C355B)
Read More
Plant 4# & 5#: 6,000 m² each
Construction Location: Nancun Town, Zezhou County, Jincheng City
Structural Form: Light Steel Structure, Portal Frame
Frame Type: Three-span, six-slope roof
Eave Height: 11.30 m
Total Length: 83.40 m
Total Width: 72.70 m
Roof Slope: 1:20
Foundation Type: Reinforced Concrete Independent Foundation
Plant 2# & 3#: 2,500 m² each
Material Specifications:
Portal Frame: C355B Grade Steel
Bracing, Purlins, Wall Girts, Channel Steel, Angle Steel, Round Steel: Q235B Grade Steel
Unspecified Steel Components: Same as Portal Frame (C355B)
Luoyang Bearing Research Institute Project
Building Area: 17,451.30 m²
Building Height: 13.60 m
Total Construction Period: 210 Days
Main Structure Type: Portal Frame Structure
Number of Above-Ground Floors: 1 Floor
Number of Underground Floors: None
Read More
Building Height: 13.60 m
Total Construction Period: 210 Days
Main Structure Type: Portal Frame Structure
Number of Above-Ground Floors: 1 Floor
Number of Underground Floors: None
Case Study of a 30,000-square-meter Steel Structure Factory
Construction area : Zhejiang
Construction area : 30000㎡
construction period : 26 weeks
Read More
Construction area : 30000㎡
construction period : 26 weeks
Construction area : Zhejiang
Construction area : 26500㎡
construction period : 16 weeks
Read More
Construction area : 26500㎡
construction period : 16 weeks
Construction area : Indonesia
Construction area : 120㎡
construction period : 1 week
Read More
Construction area : 120㎡
construction period : 1 week
Large Span Prefabricated Warehouse Steel Structure Aircraft Hangar
Construction area : Spain
Construction area : 1000㎡
construction period : 22 weeks
Read More
Construction area : 1000㎡
construction period : 22 weeks
Our C & Z purlin serves as fundamental structural elements crucial for providing support in construction projects. These purlins are meticulously engineered from robust materials, ensuring optimal strength and stability for roofing and wall systems. Available in a range of sizes and configurations, they offer versatility to accommodate diverse construction requirements. With their durable construction, our C & Z purlin guarantees dependable support and enhances the overall structural integrity of your building projects.
Read More
A box column beam is a type of beam composed of two steel plates and other components, partitioned along the axis of symmetry or at the junction of different shapes, and installed and welded in coordination with the hoisting sequence. Like H-shaped steel, it is frequently used in steel structure construction projects, typically in steel structure factories and bridge construction, serving as columns or main beams in steel structure engineering.
Read More