Luoyang LYC Bearing Co., Ltd. Project Case
Construction area : 17451.3㎡
construction period : 30 weeks
Category:
Details
Luoyang LYC Bearing Co., Ltd. New Energy Equipment Bearing Intelligent Production Base Project: Main Shaft, Gearbox Bearing, and Roller Workshop. Project Location: South side of Guanlin Road, North side of Yiluo Road, and West side of Letian Street, Luonan New District, Luoyang City.
- Building Area (m2): 17451.30
- Building Height (m): 13.60m
- Total Construction Period (days): 210
- Main Structure Type: Portal Steel Frame Structure
- Number of Floors Above Ground: 1
This project’s steel structure comprises the main shaft, gearbox bearing, and roller workshop. The basic seismic intensity of this area is 7 degrees, and the seismic fortification category of the building is Class C. The fortification intensity is 7 degrees, the basic design seismic acceleration value is 0.10g, and the design seismic group is Group II. Seismic Resistance Level: Level IV. The building site is classified as Class II, with a characteristic period of 0.4s; the fire hazard classification is Class E, with a fire resistance rating of Class II; the roof waterproofing rating is Class I, using 1.5mm thick polyester fiber reinforced (Class P) TPO waterproof membrane, installed using mechanical fixing; the exterior walls use 80mm thick rock wool sandwich panels with a fire resistance limit of 0.5h; the inner and outer color steel plates are made of galvanized aluminum steel; the steel used is Q235 steel and Q355 steel.
The main shaft, gearbox bearing, and roller mill workshop is a single-story steel structure workshop with a longitudinal length of 162m, a transverse width of 96m, a building height of 13.6m (average height from the outdoor ground level to the roof eaves and ridge), and a span of 24.000m. The foundation of this project is an independent foundation.
Luoyang LYC Bearing Co., Ltd. Project Case
Other Products
Sinosteel Luonai Simple Warehouse Construction Project EPC Contract
Sinosteel Luonai Simple Warehouse Construction Project EPC Contract
Zezhou County Zhichuang Digital Logistics Industrial Park – Phase I, Section 1
Zezhou County Zhichuang Digital Logistics Industrial Park – Phase I, Section 1: Steel Structure Works for Plant 3#, 4#, and 5#
Sanon New Material Technology (Luoyang) Co., Ltd.
Project Scale:Upon completion, the plant will produce 60,000 tons per year of high-performance extractants.
Luoyang Huijing New Material Technology Co., Ltd.
Project Overview:This steel structure project spans from axis 1-1 to 1-20 (North to South) and axis 1-A to 1-G (West to East).
Yoshida New Materials Phase I Plant Project
Total Area: 17,000 m²
Plant 4# & 5#: 6,000 m² each
Luoyang Bearing Research Institute Project
Building Area: 17,451.30 m²
Building Height: 13.60 m
Luoyang LYC Bearing Co., Ltd. Project Case
Construction area : Luoyang
Construction area : 17451.3㎡
construction period : 30 weeks
Case Study of a 30,000-square-meter Steel Structure Factory
Construction area : Zhejiang
Construction area : 30000㎡
construction period : 26 weeks
Construction area : Zhejiang
Construction area : 26500㎡
construction period : 16 weeks
Construction area : South Africa
Construction area : 320㎡
construction period : 8 weeks
Construction area : Indonesia
Construction area : 120㎡
construction period : 1 week
Large Span Prefabricated Warehouse Steel Structure Aircraft Hangar
Construction area : Spain
Construction area : 1000㎡
construction period : 22 weeks
I want to inquire
During your browsing of our products, is there anything that you find particularly satisfactory or that needs improvement? Your inquiries or suggestions will directly help us improve product and service quality, bringing you a more intimate experience.
* Please fill in the above fields (* indicates required fields), and we will reply to your feedback as soon as possible.

WeChat